Data center due diligence request builder
Build the data center due diligence request for your deal. Pick the deal type, the power in play, the state and your dates, and get a document request list built for that deal, with the items that decide it marked first.
- Right away: what to clear first, the large-load power rules in your state, and a timeline counted back from your closing date.
- When you send the brief: the full request list, with why each document matters and what to look for in it, as a spreadsheet or a PDF.
For buyers, lenders, tenants, developers and owners. Behind the list is a fixed-fee review: every document read and checked against utility filings, county records and certificate listings, in three to six weeks.
Request Builder
Step 1 of 6
What a first pass through a data room turns up
Every list the builder makes is aimed at findings like these. The drawing is an example site; each mark is the kind of problem that moves a price or a closing date.
Pick a number to highlight it on the plan.
- Power The will-serve letter names the previous developer, and it expires in March.
- Power The line upgrade in the facilities study has no in-service date.
- Title A pipeline easement runs under the planned Phase 2 hall.
- Flood Zone AE reaches the generator yard.
- Fiber The owner built the fiber across a neighbor's parcel with no recorded easement.
- Permits The generator air permit caps run hours below the tenant's test schedule.
Four numbers that change a data center model
85%
of contracted capacity billed for up to 12 years, used or not
AEP Ohio data center tariff, 25 MW and up
14 yrs
contract term for new 25 MW loads, with minimum demand charges
Dominion Energy Virginia, GS-5 class
$118,625
a year per MW of capacity obligation at PJM's $325 cap
PJM 2028/29 capacity auction
180 days
window before closing for the core Phase I steps
40 CFR 312.20 and ASTM E1527-21
Every figure on this site carries its source. The request builder flags the rules that apply in your state.
How a review works
The request list is the start. A review ends with a written due diligence report your committee can read in one sitting, and in between the work is reading: every agreement, study, report and contract the seller provides, and the public record behind each one.
You send the brief
The asset, the deal, your dates and what you already have. The Diligence Scoper or the request form covers it.
We reply within 24 hours
With questions, a written scope and one fixed fee. If the deal isn't a fit for a desk review, we say so.
The request list goes out
Built for your deal type and sent to the seller, with the items that decide the deal marked first.
We read the paper
Utility agreements and studies, title, survey, zoning, environmental reports, condition reports, contracts and the rent roll.
We check it at the source
Utility tariffs and filings, county agendas, FEMA maps, certificate listings and recorded documents, not the seller's summary.
You get the written review
Findings ranked by what they do to price, timing and the decision, each tied to the document that supports it.
Most reviews take three to six weeks from the start date. The pace is set mostly by how fast the data room fills and how fast the utility answers. The seller's response time is the part nobody controls, so the request list goes out as soon as you engage us, with the items that decide the deal at the top.
The report ranks each finding by what it does to the deal: a price adjustment, a closing condition, a timing risk, or a reason to walk away. Every finding points to the document behind it, so your counsel and lender can check it without asking us.
Six claims a data room has to back up
Offering memos lean on a handful of phrases. Each one is either backed by a specific document or it isn't, and the gap between the two is where price adjustments come from.
| What the memo says | What proves it | What we often find instead |
|---|---|---|
| "Shovel-ready" | Site plan and special use approvals read in full, with every condition and expiry date | Approvals that lapse before construction starts, or road work nobody priced |
| "Low-cost power" | The rate schedule the site will actually be billed on, minimum bill included | A general service rate quoted for a load headed for a large-load tariff |
| "Clean site" | A Phase I to ASTM E1527-21 inside the 180-day window, with PFOA and PFOS in scope | A report written for the seller two years ago |
| "Water secured" | A written commitment from the water and sewer provider for peak use | A cooling design that needs water and a provider that hasn't committed |
| "Incentives in place" | An abatement agreement that allows assignment to a buyer | A clawback that triggers on a change of ownership |
| "Strong backlog" | Signed leases whose start dates match the utility's schedule | Leases that start on power the utility hasn't committed to |
None of the right-hand column means the deal is bad. It means the price, the conditions or the timeline should reflect it. The point of the review is to know which column you are paying for.
Where the megawatts really stand
Most of the value in a data center deal comes down to how many megawatts the site can draw, from when, and on what terms. The answer sits in utility paperwork, and that paperwork comes in grades.
- An inquiry or a will-serve letter. The utility believes it can serve the load, subject to studies, upgrades and payment.
- A load or facilities study. What has to be built first, what it costs, who pays and when it is due.
- A signed electric service agreement. Megawatts, dates and obligations both sides have signed.
- Energized capacity. Power the site draws today.
We find out which grade the seller is selling, read the conditions attached, and check the utility's schedule against the ramp in the model.
The terms matter as much as the megawatts. Since 2025, several utilities and states have put large loads on long contracts with minimum bills, collateral and exit fees, and the builder flags the ones that apply in your state.
| Rule | Applies at | What it does to the deal | Source |
|---|---|---|---|
| Dominion Energy Virginia: the GS-5 class | 25 MW and up | Customers of 25 MW or more who sign a service agreement on or after January 1, 2027 fall in Dominion's GS-5 class: a 14-year contract with up to a four-year ramp, minimum demand charges of 85% of contracted transmission and distribution demand and 60% of generation demand, collateral, and three years' notice to reduce demand. | Virginia SCC final order, November 25, 2025 |
| AEP Ohio: the data center tariff | 25 MW and up | New data centers of 25 MW or more in AEP Ohio's territory pay for at least 85% of the capacity they contract for, for up to 12 years including a four-year ramp, must show financial viability, and owe an exit fee if the project is cancelled. | PUCO order, July 9, 2025, Case 24-508-EL-ATA |
| Texas: Senate Bill 6 | 75 MW and up | In ERCOT, loads of 75 MW or more pay a screening study fee of at least $100,000, must disclose duplicate interconnection requests elsewhere in Texas, and must be able to switch to backup generation or curtail in an energy emergency. | Texas SB 6, signed June 20, 2025 |
| Georgia Power: the 100 MW rule | 100 MW and up | Georgia Power customers of 100 MW or more can be billed minimum amounts on contracts of up to 15 years, and each contract is filed with the Public Service Commission at least 30 days before it is signed. | Georgia PSC rule, January 23, 2025 |
PJM's last three capacity auctions all cleared at the price cap: $329.17, $333.44 and $325 per MW-day for 2026/27 through 2028/29. At $325, that is $118,625 a year for each megawatt of capacity obligation, before any energy is bought.
What changes by deal type
The builder covers seven deal types. The workstreams are the same six on every one: power, land and permits, environment, the building, fiber, and the revenue or the lease. What moves is where the risk sits.
Buying an operating data center
Power under contract, the rent roll against the contracts, how each contract bills power, the building's real condition and certificates.
Buying a powered site or building
Whether the utility can and will serve the load, the zoning letter, floor loading and clear height, and what the conversion really costs.
Buying or leasing land to develop
The utility path from letter to signed agreement, the upgrade schedule, zoning and local opinion, flood, wetlands and water.
Leasing a hall, building or powered shell
The landlord's power position and schedule, handover dates and remedies, how the lease passes through power costs, and whether the hall can carry your density.
Financing a data center or site
The same evidence a buyer needs, read for what can impair the collateral: signed power, title and survey, environmental standing, the rent roll.
Investing in a portfolio, platform or REIT
One power schedule for every asset, backlog that depends on future power, customer concentration and power pass-through.
Getting my own site ready for buyers
The documents a buyer's team will ask for, found and fixed before they ask, so the price isn't negotiated down in diligence.
The acquisition due diligence page covers operating assets, REIT and portfolio deals and loans in depth. The property due diligence page covers land and buildings that are not data centers yet.
The Phase I clock
Environmental diligence has a hard deadline that slips past a lot of deal teams. To rely on the landowner liability protections in the federal Superfund law, a buyer's All Appropriate Inquiries must be completed within one year before acquisition, and five parts of it within 180 days. The builder counts these windows back from your closing date.
The Phase I itself should be prepared to ASTM E1527-21. EPA recognized that standard in 2023, and the older E1527-13 stopped satisfying the rule in February 2024. A report written for the seller, or one dated before the window opened, may need an update before closing.
Sustainability due diligence: energy, water and the neighbors
Buyers, lenders and the tenants behind them now ask what a data center uses, not only what it can draw. The questions land in three places: the efficiency the building really runs at, the water its cooling takes, and the local reaction that decides whether the next phase gets approved.
The scale explains the attention. A Lawrence Berkeley National Laboratory report for the Department of Energy put US data centers at about 4.4 percent of the country's electricity in 2023, with 6.7 to 12 percent projected by 2028. The same report estimates 66 billion liters of water used directly on site in 2023, most of it at hyperscale and colocation facilities.
| Measure | What to ask for | What to read it against |
|---|---|---|
| Power usage effectiveness (PUE) | Twelve months of metered PUE under ISO/IEC 30134-2, with the meter points named | The utility bills and the design figure in the memo. Uptime Institute's 2025 survey put the industry average at 1.54. |
| Water usage effectiveness (WUE) | Metered site water by month, the cooling mode by season, and the WUE method used (ISO/IEC 30134-9) | The water provider's written commitment, any drought rules, and what the sewer provider accepts back |
| Power supply and carbon | The utility's fuel mix, any renewable energy contracts or certificates, and who holds them after closing | Customer contracts that promise renewable supply. Certificates that stay with the seller don't move with the building. |
| Standing with the neighbors | Hearing minutes, complaint logs, noise readings and any agreement with the county or a neighborhood group | Conditions on the next phase, a pending moratorium, or a permit that caps generator testing |
None of this is a rating. The review reports what the meters, bills and public records show, and where the seller's sustainability claims go further than the paper. That matters most when those claims are headed into a tenant pitch, a lender's ESG reporting or your own investor letter.
What a review is not
It is not a quote, and it is not quick. A review needs the data room, the utility paperwork and your dates, and it takes weeks. If you need a number for a teaser by tomorrow, this isn't the right service.
It is not an appraisal or a legal opinion. We don't value the asset and we don't replace your counsel or your engineers.
It is not paid for by anyone but you. One fixed fee, set in writing before any work begins. We take no commission on the deal and nothing from the seller, so we are paid the same whether you close or walk away.
The team behind the reviews
Data Center Due Diligence is operated by the Metro Colo Advisory team, an independent firm that advises on data center deals. We read power, land and contract paperwork on data center deals for investors, lenders, developers and owners, and our research on utility rules and data center power is cited by the trade press.
One fixed fee, set in writing before any work begins. We take no commission on the deal and nothing from the seller, so we are paid the same whether you close or walk away.
Our team has been quoted in Fortune, Inc., Al Jazeera and Light Reading.
Read more about us, or start with the request builder.
Questions about the builder and a review
What does data center due diligence involve?
Proving what a seller, landlord, developer or borrower says about a data center or a site: that the power is contracted on known terms, the land and title are clear, the building can carry the load it is marketed for, and the contracts say what the rent roll says. A review ends in a written due diligence report that ranks each finding by what it does to price, timing and the decision.
What does the request builder give me?
A document request list tailored to your deal type, power, state and dates, with the items that decide the deal marked first. You see the priorities, the power rules for your state and your timeline right away. The full list, with why each document matters and what to look for in it, opens when you send the deal brief.
Why does the full list need my details?
Because it is built to be used on a live deal, and the brief tells us enough to answer with a scope and a fixed fee within 24 hours. Your deal stays private: no seller, broker or utility sees it unless you agree.
How long is a typical review?
Three to six weeks from the start date, set mostly by how fast the seller fills the data room and how fast the utility answers. If your exclusivity window is shorter, say so in the request and our reply will say what can be covered in the time.
What does a review cost?
One fixed fee, set in writing before any work begins. It depends on the number of assets, the deal type and how much paperwork exists, so we quote after reading the brief. We take no commission on the deal and nothing from the seller.
Do you visit the site?
No. A review is desk work: every document read and checked against utility filings, recorded documents, county records, FEMA maps and certificate listings. When a question needs someone on site, we name the report to order and the kind of firm to order it from, and we read it when it comes back.
What is technical due diligence on a data center?
It is the engineering read on the facility: the condition and remaining life of the electrical and mechanical plant, how much redundancy really exists, what the cooling can carry at full load, and the capital the next few years will need. Engineers inspect it on site. We read their report against the maintenance logs, incident history and commissioning records, and tie each finding to price.
What does ESG or sustainability due diligence on a data center cover?
Metered energy efficiency (PUE), water use (WUE) and where the water comes from, the power supply and any renewable energy contracts, and the site's standing with its county and neighbors. The work is checking each claim against meters, bills, permits and hearing records, so the figures can be used in reporting and tenant pitches. See sustainability due diligence above.
How does a review fit with counsel and the engineering report?
Counsel gives the legal opinions and negotiates the documents, and engineers inspect the equipment. We read across their work and the seller's paperwork, with power and contracts at the center, and point out where they disagree.
Can a review start before the LOI is signed?
Yes. A short screening review before you bid tells you which questions to price in. Most full reviews start at LOI or exclusivity.